Grande on Plot B4 Project Gained 4-Day Slab Cycle Record

Grande on Plot B4 Project Gained 4-Day Slab Cycle Record

During constructing Level 27 structural slab in November, Grande on Plot B4 Project achieved a 4-day slab cycle which had been recognized as a record for CSCEC ME as the fastest achieved structural slab cycle ever. Currently the structural team is maintaining a consistence of 5-day slab cycle.

Grande on Plot B4 Project is located in Downtown Dubai opera district, which is the city’s essential financial business area, adjacent to the Dubai’s landmark skyscraper Burj Khalifa.