CSCEC ME Completes Overall Basement Raft Concrete Pouring for Cavalli Casa Tower Project

CSCEC ME Completes Overall Basement Raft Concrete Pouring for Cavalli Casa Tower Project

On July 29, 2023, Cavalli Casa Tower Project accomplished the second stage of concrete pouring of 7,200 cubic meters with a 39-hour of work, and a 25-hour concrete pouring of 4,500 cubic meters on July 7, marking a significant milestone in the project’s construction.

The Cavalli project’s foundation raft consists of nearly 4,000 tons of steel bars and over 12,000 cubic meters of concrete, with a maximum depth of 8.3 meters. It is currently the largest raft foundation implemented by CSCEC ME for a single building and one of the most challenging raft constructions. Throughout the construction process, the project overcame various technical challenges, including the arrangement of 36 layers of steel reinforcement, custom-made steel-reinforced openings, and the bending and binding of curved steel bars.

The Project is a high-end 71-story residential tower in Dubai Marina by DAMAC Properties.

By | 2023-08-03T11:11:05+00:00 July 29th, 2023|News|0 Comments

About the Author:

Leave A Comment